AKINYEMI AKINDEJOYE Richmond TX, 77042 Tel: (832)-768-6885akinyemiakindejoye@gmail.com Professional
Designation: Project
Scheduler Professional Profile
Project
controls professional with solid expertise in project scheduling. Experienced
in project implementation, earned value management and project engineering. I
possess the drive to add value to any organization where my expertise are
challenged and engaged to perform at the highest optimal level
Technical Expertise Microsoft Applications │ Microsoft Office│ Microsoft
Project │Oracle Primavera P6 │Microsoft Visio│ AutoCAD│ IBM Maximo Scheduling
Software│ SAP Prometheus planning/scheduling systems Professional History British Petroleum Refinery – Whiting , Indiana
July 2015 – December 2015 Project Scheduler § Pulled
together required information to initiate an EPC plan/schedule including
scopes of work, estimate, job notes, work list and drawings. § Developed
the plan to logically execute a project with appropriate engineering and
field supervisor. § Developed
Durations and resources needed to execute the project in a timely fashion. § Produced
planning/scheduling reports on a consistent basis. § Communicated
the plan/schedule to all project team members, including client. § Monitored
progress through engineering and in the field and update the plan/schedule
accordingly. § Monitored
craft hours spent and earned, analyze productivity and its impact on project
duration. § Analyzed
the updated plan/schedule and communicated potential downstream problems
which may impact the successful completion of a project. § Walked
the field down on a regular basis. § Accounted
for Change Orders in the plan/schedule and analyze their impact on the
project. § Attended
meetings and discussed the EPC plan/schedule. Flint Hill Resources - Corpus Christi, TXSept 2013 – July 2015 Project Scheduler - Flint Hill Resource Refinery Project worth
$7million USD § Evaluated
critical paths in the project schedules and evaluate alternative schedule
options to identify optimum project strategies or resolve problems before and
during execution § Provided resource planning and project schedules for various
types of projects. § Liaised with all team leaders to communicate required
completion dates and interfaces between responsible parties § Managed and coordinated with project team members on project
schedule and interface § Uploaded Projects Schedule from MS Project to SharePoint and
PWA. (Project Web Access § Established and managed relationships with client to ensure
100 percent customer satisfaction in quality of service and commitment to
long-term relationship § Produced
reports (Man-hour productivity, schedule status, MDR- Master Data Records)
and earned value curves reports on either direct or indirect construction
activities that are a part of the work. § Worked
closely with Project Manager, and Project Management to
ensure timely delivery of project activities and make sure project objectives
are met. Baker Hughes - Houston, TXJuly 2012 -Feb 2013 Project Scheduler - Implemented an integrated scheduling plan on a two year contract for
the PMO on a variety of projects, established automated IT processes and
implemented project scheduling tools (Budget-$250 million) § Created
project schedule with 9500 line items in MS Project 2010 § Uploaded
Projects Schedule from MS Project to SharePoint and PWA (Project Web Access) § Evaluated
resource allocation with Assignment reports in MS Project § Man
loaded the Microsoft Flex schedule in the generation of manpower histograms
and Progress Curves § Tracked
and reported project schedule issues and improvement strategies to Program
Manager § Prepared
and presented status on project schedule, project deliverables, and project
risks § Reviewed
progress against plan and make recommendations to improve efficiency § Produced
reports (Man-hour productivity, schedule status, MDR- Master Data Records)
and earned value curves reports on either direct or indirect construction
activities that are a part of the work § Maintained
all subsidiary reports such as personnel staffing, release schedules,
equipment schedules to facilitate good cost projections (EAC) § Prepared
standard earned value-based reports, including schedule updates Intersea - Houston,
TX
May
2011 - June 2012 Project Scheduler(Flex LNG
Project – joint venture) § Managed
and worked as a project scheduler on the Flex LNG project, with a budget
worth about $150.5Million USD which is joint venture project with intersea § Consolidated
and analyzed information from Project Engineering, Sourcing and the
Manufacturing Project Planners to develop the overall project Schedule
(baseline time-phased schedule with proper constraints) and Work Breakdown
Structure (WBS) for assigned project sales orders § Familiar
with all facets of Scheduling from FEED / DETAIL Packages through Construction.
§ Conducted
and participated in Schedule Reviews as appropriate to ensure that schedule
requirements are being met § Participated
in weekly meetings with the Project Planners to obtain manufacturing status
(production schedules for parts, and production start dates), to update the
project schedule § Analyzed
the project schedule, monitors progress and highlights potential
cost/schedule variances. Recommends Corrective Action Plans for Project
Management approval § Analyzed
critical path and restraints to determine the effect of changes to the
schedule. Recommends work alternative solutions § Ensured
that the accounting process, including revenue and cost recognition and sales
order project activities are compliant with the Work Breakdown Structure
(WBS) Chesapeake
Energy/Access Midstream - Oklahoma City, Oklahoma March 2010 - April 2011 Project Scheduler (Douglas
Wyoming Pipeline Construction Project ) § Performed
Resource Optimization For the Pipe Line Project. § Responsible
for building project schedule with Microsoft Project by creating
Work Breakdown Structure (WBS) § Assigned
activity relationships, input activities and activity durations § Loaded
resources into the project schedule with the resource § Tracked project progress
with schedule baseline and reported activities on critical path § Performed
critical path analysis, earned value analysis, variance analysis, and
forecasting § Communicated project status
to the Project Manager, Project Management Team (PMT),
and the client § Worked
closely with Project Manager, and Project Management to
ensure timely delivery of project activities and make
sure project objectives are met § Performed
and reported schedule updates, changes and constraints to
the Project Manager § Issued
two weeks look ahead report and reviewed the reports with
the Project Management Team Cimarex
Energy - Denver, COFeb 2009 -Feb 2010 Project Planner/Scheduler(Permian
Basin Oil Field Drilling Project) § Created
and maintained detailed drilling schedules based on Work Breakdown
Structure (WBS) with task definitions, relationships, and dependencies § Worked
directly with Project Manager and functional group leads to discuss
impact of work and problem resolution § Evaluated
actual project progress and provided schedule updates § Identified
critical path activities, near critical path activities, and
advised project team accordingly § Communicated project status
report to Project Management Team (PMT) and client on
a monthly basis § Created
milestones to identify the start of work including activities that required
constraints § Assigned
duration, load activities with resources, maintained and assigned baseline
schedules for the project. URS Corporation - Houston, TXJuly 2007–Jan2009 Project Scheduler § Worked
closely with PM leadership and Project Managers to address project or
departmental activities. § Assisted
PM Leadership, Portfolio PMs, and Project Managers with administrative tasks
(tracking down and resolving issues discovered during monthly financial
updates. § Updated
actual spend/identified issues on large project plans, chasing down vendors
that have not completed status reports on time. § Set-up
large project meetings, scheduled rooms for meetings, documented minutes,
helped with the procurement process, created reports / presentations,
assisted process improvement initiatives, etc. § Assisted
VP with documenting updates, meeting coordination, set-up and notes . § Managed
the Construction project, task list and coordinated Implementations &
Development. § Facilitated
follow-up with project stakeholders and business leaders. § Produced
and distributed project related documentation and updates required for
meetings with VP. § Managed
due dates and timelines related to open projects and tasks. § Created,
maintained, monitored & controlled Master Portfolio schedule in MS
Project Dow Chemistry - Freeport, TXMay 2005 - May 2007 Project Scheduler (Oil & Gas) § Maintained
the construction schedule of Mounted Ball Valves, Floating Ball Valves, and
full opening check valves used by oil producing company. § Monitored
actual progress, compared to baseline and report progress against schedule in
primaveraP6. § Planned,
developed and setup the Integrated Schedule in Primavera for Engineering
Design, § Procurement
and Construction (EPC) schedule for the company Project. § Determined
and analyzed critical path activities on Primavera for identification of
potential delay impacts. § Guaranteed
the accuracy of the information that the Project Manager receives and, if
necessary, investigate further by checking with the field engineers if
required. § Updated,
consolidated, validated and recorded the Project Baseline Schedule from
Primavera with allthe parties actively involved. Collected and consolidated
the physical progress follow-up for projects and update it in Primavera. Education Prairie View A&M University MBA, Finance(Expected graduation 2017) Prairie View A&M University BSc. Chemical Engineering TWIC Card Holder(Transportation
Worker Identification Credential) OSHA 10 Certified Professional
Affiliation and Certifications Project
Management Institute (PMI Member) PMP
Certification in Progress (Expected completion May 2016) |
|
|
|||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||
|
|